Which of the following is an Input of Perform Integrated Change Control?
Inputs
  1. Work Performance Reports
  2. Project Management Plan
  3. Organizational Process Assets
  4. Enterprise Environmental Factors
  5. Change Requests
Tools & Techniques
  1. Meetings
  2. Expert Judgment
  3. Change Control Tools
Outputs
  1. Project Management Plan Updates
  2. Project Documents Updates
  3. Change Log
  4. Approved Change Requests